Page 223 - _ 180314 Special Yucaipa GSA Packet
P. 223

arrangement including the proposed basin, proposed soil   Task 2.0 Infiltration Testing at
        stockpile locations, piping, traffic control, and site safety
        features in plan form. The draft work plan will contain site   13 Sites
        specific BMPs for soil excavation, stockpiling, and protection
        of channels, and any facilities at each site. The work plan   2.1 Fabrication of Needed Equipment
        will be submitted for initial review to the project team.
                                                               Once our work plan has been finalized, our subcontractors
        1.4 Progress Meeting and Finalization of               will begin planning for field work by finalizing site access
                                                               and water source locations with Valley District staff and
        Work Plan                                              other affected parties. Other Equipment Subcontractors
        After receipt of work plan comments, we recommend      (Intuitech Inc. and Southland Water Technologies LLC)
        a progress meeting to discuss comments and/or other    will begin fabricating the needed instrumentation and
        site considerations presented by the project team before   inlet facilities needed for excavated pit testing. If the,
        finalizing the draft work plan. The final draft work plan will   containerized infiltration basin option is chosen, then
        be submitted to SBCFCD for their review, comment, and   fabrication would also include converting the containers
        approval followed by the final work plan which will address   and installing piping and instrumentation within the
        and incorporate any comments provided by SBCFCD. The   container. We will coordinate with the contractor and
        final work plan will be submitted to the project team and   oversee these activities.
        SBCFCD as a part of the permitting process.
                                                               2.2 Conduct Infiltration Testing and
        1.5 Project Management and Permit                      13 Sites
        Support                                                IO Environmental will begin by mobilizing all equipment
        Project Management tasks will include four face-to-face   to the site. For alternative A using excavated pits per your
        meetings(1 site visit/kick-off meeting, 2 draft workplan   RFP, We will begin digging 30-foot by 30-foot test basins
        progress meeting, and 1 pre-construction meetings with   with a 1:1 sloped wall where possible. If site conditions do
        Valley District, SBCFCD, and the subcontractor, and 1   not permit, a smaller test basin will be constructed per the
        meeting to present the final results of the testing after   work plan.
        submission of the draft summary report).
                                                               For our proposed alternative B, containerized infiltrometers
        The kick-off meeting will be combined with site visits to   will be set at the site using either a crane or forklift
        review logistical issues for the testing, establish chain   depending on conditions. Excavation is minimal for this
        of command for site reporting,  have initial discussion   alternative and there is no anticipated soil storage.
        on proposed site lay-outs for the testing, and discuss
        any opportunities for coordination with local staff from   For alternative A, excavated material will be stored at
        participating agencies for field monitoring activities. The   each site according to the site plan and using the BMP
        purpose and content of the draft work plan meeting is   requirements for each site.  Excavated soils may be
        discussed above. Finally, after submission of the draft   temporarily stored adjacent to test basin on channel
        report summarizing the project findings, we will present   banks. Where possible and allowed, we will use excavated
        the findings to the project team and discuss any comments   materials to create a shallow berm around the test basin.
        prior to preparing a final report.                     We will then set up water conveyance, flow control system,
                                                               backflow prevent, solar generator, and basin source water
        Also, draft results from infiltration testing at each basin   manifold. If onsite water is unavailable, we will set up a
        will be provided to the project team followed by a     water tank and pump.
        teleconference to discuss the results and any issues that
        may have arisen during the testing period at each basin.   Once the basin is constructed, the subcontractor will
        Due to the many sites and generally open access to sites,   conduct an initial test of the installation to verify that
        any unforeseen issues or interferences at the test sites   instruments are operating properly and the water
        will be immediately reported to project manager with a   conveyance system is sound. Once pre-startup tests are
        summary correspondence sent to the project team for    complete, and the system is recording data, testing will
        action as appropriate.                                 begin by filling the basin at an initially high rate.
                                                               When testing is completed, IO Environmental staff will
        Task 1.0 Deliverables                                  demobilize equipment once the basins have completely
                                                               drained and to return the site to pre-test conditions. IO will
        We understand that the Task 1 deliverables will include the   then transport equipment to the next location.
        following:
                                                               Because the site will be largely unattended, site safety
        •  P&ID of water conveyance, instrumentation and control  and security will be a concern. We will install site fencing
        •  Draft (100%) and Final Pilot Recharge Test and      and signage to deter vandalism and theft. Additionally, the
            Monitoring Plan Final Plan that includes detailed site   control system will be automated and monitored remotely.
            plans and BMPs for each site.                      Alarm triggers will be set on either low line pressure or high
        •  Electronic Files to be provided in required format at the   water level in the basin and the system will notify us so we
            completion of the task. 1.1                        can respond as necessary.





                                  Yucaipa Groundwater Sustainability Agency - March 14, 2018 - Page 197 of 226      5
   218   219   220   221   222   223   224   225   226   227   228