requirements and meet temporal and spatial monitoring objectives to support continued evaluation of the
effectiveness of the GSP. Includes a preliminary study of available information and data evaluation of
screened intervals with respect to aquifer zones based on existing logs. The memorandum will be subject to
one (1) round of review by the Yucaipa GSA.
Deliverables:eliverables:
D
Deliverables:Deliverables:
• One (1) electronic copy of the Monitoring Network Technical Memo (which will constitute the
majority of the “Existing and Planned Monitoring” chapter of the GSP).
Technical Assessment of Projects and Actions
Dudek assumes that project costs, costs associated with implementing management actions, and
anticipated acre-feet of water supplied, will be provided by the project proponent, Yucaipa GSA member
agencies, or stakeholders. Dudek will produce an initial memo documenting the technical assessment of
projects and management actions after coordination with the Yucaipa GSA and stakeholders during the
first projects and management actions discussion session. Up to one (1) additional memo will be
prepared following the second discussion session to reflect updated analyses provided by project
proponents, additional management actions contemplated by the Yucaipa GSA, and the results of the
groundwater modeling efforts.
eliveeliverables:rables:
D DD Deliveeliverables:rables:
• One (1) electronic copy of the Initial Projects and Management Actions Technical Memo
• One (1) electronic copy of the Second Projects and Management Actions Technical Memo
Prepare GSP
A
Administrativedministrative Draft GSPDraft GSP
AdministrativeAdministrative Draft GSPDraft GSP
Dudek anticipates completing the administrative draft of the GSP in July 2020. The administrative draft
will be provided electronically to the Yucaipa GSA o review and provide comments. Dudek anticipates a
60-day review period for the administrative draft. Dudek anticipates that the member agencies will
coordinate their comments and provide either a single comment document from the entire GSA or a
single comment document from each GSA member agency.
• Dudek will respond to 100 comments.
D
Draft GSPDraft GSP
Draft GSPraft GSP
Dudek will incorporate the comments made on the administrative draft and submit (electronically only) a
final red-line draft document as a check copy to the Yucaipa GSA before preparing the draft GSP for
public review. The check copy will be provided to the GSA one week before release to the public. It is
anticipated that the comments received on the check copy will be minimal and mostly editorial in nature.
Substantive comments requiring a second round of substantial edits would require an amendment to the
proposed budget. Dudek assumes the Draft will be released to the public in January 2021, and that the
comment period will close in February 2021.
Respond to Comments on Draft GSPespond to Comments on Draft GSP
Respond to Comments on Draft GSPRespond to Comments on Draft GSP
R
Responses to comments will be generated following closure of the comment period in February 2021.
Dudek assumes that no more than 20 substantive discrete comments will be received on the Draft GSP;
note that one comment letter can contain multiple substantive comments. Since the actual scope and
extent of public comments (in either written or oral format) cannot be definitively determined at this time,
if additional staff hours are needed to prepare responses to comments, the scope of work and budget
provided in this proposal would be amended.
Page C-8