3  Assumptions




               Dudek provides the following cost assumptions used in development of the fixed-price items outlined in
               the budget estimate.


               Assumptions for Development of GSP


               GSP Development

               Dudek Assumes the project will last 28 months.  This is an escalation of the original schedule, but
               reduces costs associated with meetings and project management.

               Project Facilitation, Project Management, and Meetings
               P
               Project ManagementProject Management
               Project Managementroject Management

               Weeklyeekly  Project Phone CallsProject Phone Calls
               W
               WeeklyWeekly  Project Phone CallsProject Phone Calls
               We have budgeted one (1) hour per week for the duration of the project for update phone calls with the
               GSA point of contact and one (1) additional hour per week for additional communication.  The phone calls
               will be conducted by either the project manager or other team members.
               Progress Reports and Schedule Updatesrogress Reports and Schedule Updates
               Progress Reports and Schedule UpdatesProgress Reports and Schedule Updates
               P
               Dudek will prepare monthly project reports and schedule updates that will identify the percentage of the
               budget by task that has been expended to date, the upcoming work and schedule, scope, or budget
               concerns identified during the billing period. Dudek anticipates preparing up to 28 monthly progress
               reports, beginning in fall 2018.  Estimated time for progress reports and invoicing is six (6) hours per
               month.
               Monthly onthly YucaipYucaipa GSAa GSA  MeetingsMeetings
               M
               Monthly Monthly YucaipYucaipa GSAa GSA  MeetingsMeetings
               Dudek will participate in eight (8) GSA meetings. Each meeting is assumed to require twelve (12) hours
               for meeting preparation, presenting at meetings, and travel.  It is assumed that all 8 meetings will be
               attended by the project manager and four (4) will be attended by Dr. Weinberger. Dudek assumes Valley
               District or Yucaipa GSA member agencies will reserve the meeting location. The tentative topics for
               presentation to the GSA are:

                   1.  Kickoff, project organization, request for historical  and current data
                   2.  Conceptual Model,
                   3.  Current conditions, historical water budget, historical safe yield, data gaps, uncertainty
                   4.  Sustainability: undesirable results, minimum thresholds and measureable objectives
                   5.  USGS model uncertainty, and establishing future conditions to be simulated: climate, population
                       growth and demand, projects to be evaluated
                   6.  Review simulations of future conditions and estimated sustainable yield, re-visit undesirable
                       results, minimum thresholds and measureable objectives
                   7.  Review of comments on administrative draft GSP
                   8.  Review of comments from public review



                                                                                                     Page C-5